Scope of Works:
HH Civil were contracted by Spaceframe Pty ltd for the Detailed Earthworks, Supply and Installation of 6km of Stormwater, ranging in diameter from 300mm – 750mm and over 50 drainage structures and installation of other external services. In order for structural and hardstand formations to continue at the scheduled progress, HH Civil were required to complete 90% of the scope within the first 5 weeks of commencing.
Project highlights:
With a near impossible timeframe HH Civil was able to mobilise and procure equipment to hit the ground running and ensure that the clients schedule did not slip regardless of the delayed start to the project.
Responsible for the procurement, installation and commissioning of 6km of stormwater consisting of 53 structures, ranging from 300mm to 750mm diameter pipeline and other site services
With a strong quality and safety culture in the business HH Civil was able to complete the project professionally and safely. Ensuring that the completion of the job was just as good as the start, completing on time and budget.