Location: Laidley QLD
End User: QUU
Completion Date: September 2020
Scope of Works:
Scope included various Structural Mechanical and Piping elements of the STP;
- New Inlet works and associated services
- New potable water pipeline into the site
- PST Dosing
- Control Room construction
- Hydraulic Enhancement
- MF Backwash and Supernatant
- Co2 Dosing
- Conduit Installation
Project highlights:
1.5km of water and sewer rising mains
300m of 450mm dia Gravity Sewer pipe and MH
Various live works cut-ins without disruption to existing operations.
No underground service strikes
Zero Incidents and Scope complete ahead of schedule